We read all 50 sheets in the index and found 13 RFIs to send your design team: 9 conflicts, 1 missing number, and 3 notes that send you to a document that isn’t in the set. The set also calls for 10 submittals, 7 special inspections, 5 long-lead items, 4 owner-furnished items, 7 utility and permit items, and 6 closeout items, each listed below with its sheet. The spec book, and two sheets the drawings refer to, were not part of this read.
Here’s what a report looks like.
Every full report follows the same layout, so your team knows where to look. Your free view shows your top potential change order in full, like RFI 1 below, with a preview of other items the free read found.
Ten parts, always in this order.
- 1
Cover page
One page you can forward to your architect, your lender or your board.
- 2
Project header
The project, the set, the sheet index, and every sheet that was read.
- 3
RFIs
Conflicts, disagreements and missing numbers, each with the question to send.
- 4
Submittals
Every submittal the drawings call for, with its sheet.
- 5
Special inspections
The inspections and tests the drawings require.
- 6
Long-lead items
Equipment and materials to order early.
- 7
Owner-furnished items
What the owner buys, who installs it, and what it needs.
- 8
Utilities and permits
Services, utility work, permits and approvals.
- 9
Closeout items
Manuals, as-builts, training, warranties and spares.
- 10
Not in this read
Anything the drawings refer to that wasn’t in the set.
A full report,
start to finish.
- Project
- One-story commercial building, new construction on a vacant site (not named)
- Set
- Bid set
- Sheets in index
- 50
- Sheets read
- 50
- Not in this read
- The spec book, and two sheets the drawings refer to: S3.1 and A0.3
- Sheets
- C1 to C4 civil general note 2 · C1 note at the dumpster pad · S3.0 dumpster pad detail
- C1 to C4 say
- “All concrete pavement and dumpster pad to be 6" D.G.A. and 6" 3500 psi concrete with 6x6x6 WWM.”
- C1, at the pad
- “Concrete dumpster pad shall be 8" 4000 psi concrete with fiber reinforcement with #4 rebar placed 12" o.c. in both directions … placed on 8" of compacted D.G.A.”
- S3.0 says
- The dumpster pad detail refers to 1/S3.1, a sheet that isn’t in the set.
- Question to send
- Which section governs the dumpster pad: 6" of 3,500 psi concrete with WWM on 6" of DGA, or 8" of 4,000 psi with fiber and #4 bars at 12" each way on 8" of DGA? And please issue detail 1/S3.1.
- Why it matters
- Thickness, strength, reinforcing and base all change, so the two sections price differently.
- Sheets
- A1.1 enlarged plan · A1.1 bollard detail 22
- The plan says
- “4" dia. x 4'-0" high concrete filled bollards.”
- Detail 22 says
- “6" Ø standard stl. pipe … solid fill.”
- Question to send
- Which bollard is required at the trash enclosure: the 4" concrete-filled bollard on the plan, or the 6" standard steel pipe in detail 22?
- Sheets
- P2.0 plumbing fixture schedule · A0.2 accessibility notes
- P2.0 says
- “ADA compliant 18" rim height.”
- A0.2 says
- “Urinals shall be wall hung with elongated rim 16-1/2" maximum.”
- Question to send
- What rim height governs for the accessible urinal: 18" on P2.0, or 16-1/2" maximum on A0.2?
- Why it matters
- Accessible fixtures are checked at inspection, so the height is easiest to settle before rough-in.
- Sheets
- E1.0 electrical site plan · E4.0 general note A
- E1.0 says
- “New utility pole with pole mounted transformers and secondary riser to underground. Coordinate with utility company.”
- E1.0, note 7
- “Provide (2) 4" conduits from utility connection point to new transformer pad. Coordinate and confirm with utility.”
- Question to send
- Is the new service from pole-mounted transformers (E1.0 and E4.0 note A), or from a transformer on a new pad (E1.0 note 7)?
- Why it matters
- A pad-mounted transformer adds a pad and conduits, and changes the coordination with the utility.
- Sheets
- E0.1 general notes · E4.0 feeder table
- E0.1 says
- “All building wiring (THHN/THWN) shall be insulated copper conductors.”
- E4.0 says
- Feeder F1 is listed steel/aluminum; the other feeders are steel/copper.
- Also on E0.1
- “Conductors #1/0 and larger are allowed to be aluminum with engineer’s approval.”
- Question to send
- Is feeder F1 copper or aluminum? If aluminum, is this the engineer’s approval under E0.1?
- Why it matters
- Copper and aluminum feeders are sized and priced differently.
- Sheets
- C5 separator detail, and its callout on C4
- C5 shows
- The “site specific data requirements” table is printed with every value blank: water quality flow rate, peak flow rate and its return period, rim elevation and pipe data.
- Also on C5
- “Engineer of record to confirm actual groundwater elevation.”
- Question to send
- Please provide the site-specific data for the separator, and the groundwater elevation.
- C1, C2, C4RFI 7 · Site security lightingConflict. C1: “No security lighting will be provided for the site.” C2 and C4: “Pole security lighting will be provided for the site.” General note 17 on C1 to C4: mounted on the buildings.
- C1, A1.1RFI 8 · Trash enclosure finish and gatesConflict. C1: block walls with an exterior stucco finish and composite gates. A1.1: brick masonry veneer with cast stone coping, and steel and metal-panel gates painted black.
- S2.0, M2.0RFI 9 · RTU-1 weightConflict. The roof framing plan carries RTU-1 at 769 lb; the mechanical schedule at 900 lb.
- P3.0, P2.0RFI 10 · Water heater fuelConflict. The water heater detail labels the gas line LPG; the gas riser and the pipe schedule say natural gas.
- E3.0RFI 11 · Transformer groundingSent to a document not in the set: “Transformer grounding per utility provider’s specification.”
- C1 to C4RFI 12 · Storm water stabilizationSent to a document not in the set: the erosion notes cite “the guidance document for storm water management” without naming it.
- A1.1RFI 13 · Accessible parking signageSent to a sheet not in the set: the signage callout refers to A0.3.
- A0.0Millwork and wood constructionShop drawings
- A0.0Metal fabricationsShop drawings
- A0.0Glazing systems and glass doorsShop drawings
- A0.0Fire suppression systemsShop drawings
- A0.0Above-ceiling coordinationCoordinated shop drawings of ceiling heights, fixtures, conduit, piping, sprinkler lines and ductwork
- A2.3CanopiesSealed, engineered shop drawings by the contractor
- A2.3Exterior access ladderDelegated design to ICC, OSHA 1910.28 and ANSI A14.3
- S0.0Structural steelComplete shop drawings for the engineer’s approval
- S0.0, CF10Cold-formed steelComplete shop drawings for the engineer’s approval
- MEP0.0Pipe supports and hangersShop drawings and PE-stamped calculations for any hanger load over 500 lb
S0.0: by an independent agency employed by the owner.
- S0.0SoilsIBC 1705.6: materials below footings, excavation depth, fill testing, lift thickness and density, and the prepared subgrade
- S0.0Concrete constructionIBC 1705.3
- S0.0Open-web steel joists and joist girdersIBC 1705.2.3: installation, end connections and bridging
- S0.0Steel other than structural steelIBC 1705.2.2: cold-formed steel framing
- S0.0WeldingWelder identification, joint preparation, equipment settings, travel speed, materials and shielding gas
- S0.0Roof and deck weldsPer the special inspection schedule
- S0.0FabricatorsIBC 1704.2.5
A0.0 asks for a list of any deliveries that would delay completion, within 5 days of contract.
- M1.0, S2.0Rooftop units RTU-1 to RTU-5Factory-built equipment
- E4.0600A fused disconnect switch, NEMA 3RElectrical service equipment
- S0.0Steel joists and joist girdersDesigned by the joist manufacturer, then fabricated
- A5.1, A5.2Aluminum storefront and glass doorsShop drawings come first (A0.0)
- A2.3CanopiesSealed shop drawings come first, then fabrication
- A10.1ULT freezers (OFOI)Owner furnished, owner installed.Work to finish before the freezer vendor arrives, starting with a slab tolerance of 1/4" in 10′ and a complete roof.
- A2.1Commercial-grade shelving (OFCI)Owner furnished, contractor installed.
- A6.1iPad mountsBy the owner, on the mullions.Needs conduit; the route is on the electrical sheets.
- A3.1Building signage (OFOI)Permitted and installed by others.
- E1.0Electric serviceNew utility pole with pole-mounted transformers and a secondary riser to underground. Coordinate with the utility.E0.1: apply for temporary and permanent service, with permitting, inspection and fees.
- E1.0CommunicationsUnderground 2" conduit with pull string to the building, and an empty 4" conduit with pull string from the utility pole.
- C1 to C4Water service1" type K copper
- C1 to C4Sanitary sewer serviceSDR 35 piping
- A0.0, MEP0.0PermitsThe contractor obtains and pays for all applications, permits and inspections.
- A0.1Deferred submittalsFire alarm drawings, by an approved fire alarm installer. Exterior signage, by the signage vendor.
- C1Sidewalks and rampsBuilt to ADA standards and inspected by the state highway department as part of the permit process.
- A0.0Operation and maintenance manualWarranties, product literature and maintenance schedules by CSI division, in binders: one copy for the architect’s review, then two for the owner.
- MEP0.0MEP operation and maintenance dataOne PDF with a cover and index: operating and maintenance instructions, parts lists, warranties and the final approved submittals for each piece of equipment.
- A0.0As-builtsMarked-up as-built documents and as-built electronic files, before final payment.
- MEP0.0Start-up, commissioning and trainingStart-up and commissioning support, help for the test and balance contractor, and training for the owner’s maintenance staff.
- MEP0.0, A3.1WarrantiesA one-year guarantee on the work in the MEP notes, and a roofing warranty of 15 years minimum.
- E0.1Spare fusesA duplicate set of each size installed, turned over in a spare fuse cabinet.
- Project manualSpecifications: not part of this read
- S3.1Referred to by the dumpster pad detail on S3.0; not in the set
- A0.3Referred to by the accessible parking signage on A1.1; not in the set
Want this for your own set?
Uploads open soon. Then you’ll see your top potential change order free in 15 minutes or less, with no credit card required, and your full report runs at checkout.