- Sheets
- G0.0 G0.1
- What we found
- Sprinkler work stated as none, but GC sprinkler contractor has a deferred submittal
- G0.1 says
- “10. FIRE PROTECTION: THE EXISTING AUTOMATIC SPRINKLER SYSTEM (NFPA 13) TO REMAIN. NO SPRINKLER WORK IN THIS CONTRACT.”
- G0.0 says
- “NO.: 2 · DEFERRED SUBMITTAL: FIRE SPRINKLER MODIFICATIONS AND HYDRAULIC CALCULATIONS · PREPARED BY: GC'S FIRE SPRINKLER CONTRACTOR”
- Question to send
- Ask the architect to confirm in writing whether the sprinkler modifications, heads and hydraulic calculations are in the GC's contract.
- Why it matters
- G0.1 says no sprinkler work is in this contract. G0.0 deferred submittal no. 2 gives sprinkler modifications and hydraulic calculations to the GC's fire sprinkler contractor, and A2.0 requires head relocation and added heads by that contractor.
- Impact
- High impact
Hale Commons Diner
Every item SheetRisk found, by impact. Try everything: this copy is yours.
A mock-up drawing set, with real problems. The project, its firms and its 13 drawings are a mock-up made for this demo. The problems drawn into them aren’t made up: they come from real drawing sets we ran through SheetRisk, with the names and numbers changed. Every item on this board is what SheetRisk found when it read this set, unedited, and the same kinds of items it finds on real sets. Anything you change here resets when you leave the page.
This sample is a small drawing set of 13 sheets. Larger sets generally turn up more items. It’s easier to read on a computer.
Loading the sample report…
High impact 18 items
- Sheets
- P1.0 E1.0
- What we found
- Water heater WH-1 input is 18 kW on plumbing and 12 kW on electrical
- P1.0 says
- “TAG: WH-1 · TYPE: ELECTRIC, COMMERCIAL TANK TYPE · STORAGE: 80 GAL · INPUT: 18 KW · VOLTS / PH: 208 / 3 · RECOVERY: 74 GPH AT 100 F RISE · NOTES: STORE AT 140 F. MIXING VALVE TO 120 F AT THE HAND SINKS.”
- E1.0 says
- “CKT: 18 · DESCRIPTION: WH-1 WATER HEATER, 12 KW · VA: 5,530 · BKR: 3 · BKR: 3 · VA: 4,000”
- Question to send
- Is the WH-1 input 18 kW or 12 kW?
- Why it matters
- P1.0 schedule gives WH-1 an 18 kW input. E1.0 circuit 18 describes WH-1 as a 12 kW heater.
- Impact
- High impact
- Sheets
- P1.0 K1.0
- What we found
- Grease interceptor sized 1,000 gallons on plumbing and 750 on kitchen schedule
- P1.0 says
- “3. GREASE WASTE: ALL FLOOR SINKS AND KITCHEN WASTE DRAIN TO A 1,000 GALLON EXTERIOR GREASE INTERCEPTOR, GI-1. SEE THE CIVIL DRAWINGS FOR THE INTERCEPTOR LOCATION AND THE SITE PIPING.”
- K1.0 says
- “ITEM: 20 · QTY: 1 · DESCRIPTION: GREASE INTERCEPTOR, 750 GALLONS, EXTERIOR · BY: GC · SET BY: GC · ELECTRICAL: - · PLUMBING: GREASE WASTE · GAS: - · REMARKS: SIZED BY THE KES. SEE NOTE 6”
- Question to send
- Is the grease interceptor 750 gallons or 1,000 gallons?
- Why it matters
- P1.0 note 3 sends all grease waste to a 1,000 gallon interceptor GI-1. K1.0 item 20 and note 6 size the interceptor at 750 gallons.
- Impact
- High impact
- Sheets
- G0.0 G0.1 P1.0
- What we found
- Gas service: base bid 2 PSI landlord service vs 7 in. w.c. utility meter
- G0.0 says
- “6. BASE BID: THE EXISTING 2 PSI GAS SERVICE AND METER ARE PROVIDED BY THE LANDLORD. ALTERNATE NO. 1: PROVIDE A NEW GAS SERVICE AND METER FOR THE TENANT. STATE THE ALTERNATE AS AN ADD OR A DEDUCT ON THE BID FORM.”
- G0.1 says
- “ITEM: GAS SERVICE AND METER (BASE BID) · BY LANDLORD: YES, 2 PSI · BY TENANT (GC): PIPING FROM THE METER · NOTES: SEE ALTERNATE NO. 1, G0.0”
- P1.0 says
- “1. GAS SERVICE: A NEW TENANT GAS METER AND SERVICE AT 7 IN. W.C. ARE PROVIDED BY THE UTILITY. THE GAS PIPING IS SIZED FOR 7 IN. W.C. LOW PRESSURE WITH A 0.5 IN. W.C. PRESSURE DROP. NO PRESSURE REGULATORS ARE REQUIRED.”
- Question to send
- Ask the engineer and landlord which gas pressure and meter source govern the base bid and whether regulators are needed.
- Why it matters
- G0.0 note 6 and G0.1 give the base-bid gas service and meter to the landlord at 2 PSI. P1.0 note 1 gives a new utility meter at 7 in. w.c. with no regulators and sizes the piping for that pressure.
- Impact
- High impact
- Sheets
- A3.0 K1.0
- What we found
- Walk-in floors: slab depressed for quarry tile vs prefab floors on existing slab
- A3.0 says
- “2. WALK-IN COOLER 104 AND FREEZER 105: DEPRESS THE SLAB 4" AND INSTALL QT-1 QUARRY TILE INSIDE THE WALK-INS, FLUSH WITH THE KITCHEN FLOOR. COORDINATE THE DEPRESSION WITH THE WALK-IN MANUFACTURER BEFORE THE SLAB IS CUT.”
- K1.0 says
- “7. WALK-IN COOLER AND FREEZER: PREFABRICATED INSULATED FLOORS BY THE WALK-IN MANUFACTURER, SET ON THE EXISTING SLAB. PROVIDE AN INTERIOR ALUMINUM RAMP AT EACH DOOR.”
- Question to send
- Which walk-in floor is built, the depressed slab with quarry tile or the prefabricated floor on the existing slab?
- Why it matters
- A3.0 notes 2 and 4 depress the slab 4 in. at walk-ins 104 and 105 for flush quarry tile; K1.0 note 7 sets prefabricated insulated floors on the existing slab.
- Impact
- High impact
- Sheets
- K1.0 M1.0
- What we found
- MAU-1 VFD: M1.0 schedule calls for a VFD; K1.0 note 3 says none
- K1.0 says
- “3. MUA-1: TWO-SPEED MAKE-UP AIR FAN CONTROLLED FROM THE HOOD CONTROL PANEL. NO VARIABLE FREQUENCY DRIVE.”
- M1.0 says
- “TAG: MAU-1 · SERVES: KITCHEN HOOD · CFM: 2,900 · HEATING: GAS, 300 MBH INPUT, 55 F DISCHARGE · HP: 2 · DRIVE: DIRECT DRIVE WITH VFD. VFD FURNISHED BY THE MC · VOLTS / PH: 208 / 3 · MCA: 12.0 · MOCP: 15 · WEIGHT: 640 LB · NOTES: INTERLOCK WITH EF-1 AT THE HOOD CONTROL PANEL”
- Question to send
- Does the make-up air fan have a VFD, who furnishes it, and what is the correct unit tag?
- Why it matters
- K1.0 note 3 calls the make-up air fan MUA-1, two-speed with no variable frequency drive. M1.0 schedule tag MAU-1 is direct drive with a VFD furnished by the MC.
- Impact
- High impact
- Sheets
- G0.1 E1.0
- What we found
- Building fire alarm tie-in is assigned to the landlord's FA contractor on G0.1 and to the electrical contractor on E1.0
- G0.1 says
- “11. FIRE ALARM: TENANT NOTIFICATION DEVICES PER FA1.0. THE TIE-IN TO THE BUILDING FIRE ALARM SYSTEM IS MADE BY THE LANDLORD'S FIRE ALARM CONTRACTOR AT THE TENANT'S COST.”
- E1.0 says
- “8. CONNECT THE TENANT FIRE ALARM CONTROL PANEL TO THE BUILDING FIRE ALARM SYSTEM. THE CONNECTION IS MADE BY THE ELECTRICAL CONTRACTOR.”
- Why it matters
- G0.1 says the landlord's fire alarm contractor makes the tie-in at the tenant's cost, and the landlord/tenant matrix shows the tenant only pays. E1.0 says the electrical contractor makes the same connection. The landlord's contractor sits outside the GC contract, so the split changes who prices and performs the tie-in. Question: Confirm in writing who makes the tenant FACP-to-building FA connection and what the GC must price, including any cost for the electrical contractor's connection work.
- Impact
- High impact
- Sheets
- G0.1 E1.0
- What we found
- Meter socket: landlord furnishes on E1.0, EC furnishes on G0.1
- G0.1 says
- “ITEM: METER SOCKET AND CT CABINET · BY LANDLORD: - · BY TENANT (GC): YES, BY THE EC”
- E1.0 says
- “METER M-104 NEW METER SOCKET IN THE LANDLORD METER STACK, FURNISHED AND INSTALLED BY THE LANDLORD”
- Question to send
- Who furnishes and installs meter M-104 and the CT cabinet, and should the EC scope change?
- Why it matters
- G0.1 Table T2 gives the meter socket and CT cabinet to the tenant GC by the EC, while E1.0 says the new meter socket in the landlord meter stack is furnished and installed by the landlord.
- Impact
- High impact
- Sheets
- G0.1 A5.0 A1.0
- What we found
- Door 101 needs panic hardware per G0.1, but HW-1 lists deadlock and thumbturn
- G0.1 says
- “6. DOORS 101 AND 107 SERVE AN A-2 OCCUPANCY WITH AN OCCUPANT LOAD OF 50 OR MORE AND SHALL HAVE PANIC HARDWARE (IBC 1010.2.9).”
- A5.0 says
- “1 STOREFRONT DEADLOCK WITH KEY CYLINDER AND THUMBTURN”
- A1.0 says
- “1 EXISTING STOREFRONT TO REMAIN. PROVIDE NEW ENTRY HARDWARE AT DOOR 101; SEE THE DOOR SCHEDULE ON A5.0.”
- Question to send
- Confirm whether HW-1 must be revised to a listed panic or exit device, and price the device, storefront modification and keying change if so.
- Why it matters
- G0.1 note 6 requires panic hardware on doors 101 and 107 for an A-2 occupant load of 50 or more. A5.0 HW-1 for door 101 lists a storefront deadlock with key cylinder and thumbturn and no panic or exit device.
- Impact
- High impact
- Sheets
- G0.0 G0.1 S1.0 M1.0
- What we found
- Roof curb work is assigned to the GC, MC, fan maker and landlord's roofer
- G0.1 says
- “ITEM: ROOF AND ROOF WARRANTY · BY LANDLORD: EXISTING · BY TENANT (GC): PENETRATIONS AND CURBS · NOTES: USE THE LANDLORD'S ROOFER”
- G0.0 says
- “11. COORDINATE ALL ROOF WORK WITH THE LANDLORD'S ROOFING CONTRACTOR TO KEEP THE ROOF WARRANTY IN FORCE.”
- S1.0 says
- “3. ROOF CURBS, OPENINGS AND OPENING FRAMES FOR RTU-1, MAU-1, EF-1 AND EF-2 ARE FURNISHED AND INSTALLED BY THE MECHANICAL CONTRACTOR.”
- M1.0 says
- “TAG: EF-1 · SERVES: KITCHEN HOOD · TYPE: UPBLAST, GREASE RATED · CFM: 3,600 · ESP (IN.): 1.75 · HP: 2 · VOLTS / PH: 208 / 3 · WEIGHT: 145 LB · NOTES: ROOF CURB: 20" VENTILATED CURB WITH HINGE KIT, FURNISHED BY THE FAN MANUFACTURER AND INSTALLED BY THE GC.”
- Question to send
- Ask the architect which party furnishes and installs each curb and whether the landlord's roofer must set them.
- Why it matters
- G0.1 says use the landlord's roofer for penetrations and curbs, and G0.0 requires roof work coordinated with that roofer to keep the warranty. S1.0 says the MC furnishes and installs the curbs, and M1.0 says the EF-1 curb is furnished by the fan manufacturer and installed by the GC.
- Impact
- High impact
- Sheets
- A1.0 A4.0
- What we found
- Sheet A5.1 is referred to but not in the set
- A1.0 says
- “3/A5.1”
- A4.0 says
- “3/A5.1”
- Question to send
- Please issue sheet A5.1, or say which sheet in the set carries that information.
- Why it matters
- A1.0, A4.0 refer to sheet A5.1 (2 references), but it is not in the drawing set. What it shows is not in the bid documents.
- Impact
- High impact
- Sheets
- G0.1
- What we found
- Fire alarm device layout is on FA1.0, which is not in the set
- G0.1 says
- “11. FIRE ALARM: TENANT NOTIFICATION DEVICES PER FA1.0. THE TIE-IN TO THE BUILDING FIRE ALARM SYSTEM IS MADE BY THE LANDLORD'S FIRE ALARM CONTRACTOR AT THE TENANT'S COST.”
- Question to send
- Please issue FA1.0 so the notification device count, locations and conduit can be priced.
- Why it matters
- G0.1 note 11 says tenant notification devices are per FA1.0, and E1.0 also refers to FA1.0, but FA1.0 is not in this set.
- Impact
- High impact
- Sheets
- P1.0
- What we found
- Water heater WH-2 is shown on plan but not in the schedule
- P1.0 says
- “7. THE RESTROOM LAVATORIES ARE SERVED BY A POINT-OF-USE WATER HEATER, WH-2, ABOVE THE CEILING IN EACH RESTROOM.”
- P1.0 says
- “TAG: WH-1 · TYPE: ELECTRIC, COMMERCIAL TANK TYPE · STORAGE: 80 GAL · INPUT: 18 KW · VOLTS / PH: 208 / 3 · RECOVERY: 74 GPH AT 100 F RISE · NOTES: STORE AT 140 F. MIXING VALVE TO 120 F AT THE HAND SINKS.”
- Question to send
- What are the size, input, voltage and recovery for WH-2?
- Why it matters
- P1.0 note 7 and LAV-1 use WH-2 for lavatory hot water. The water heater schedule on P1.0 carries only WH-1.
- Impact
- High impact
- Sheets
- P1.0 G0.1
- What we found
- Civil drawings and landlord site plan for grease interceptor not in set
- P1.0 says
- “6" GW TO THE 1,000 GALLON EXTERIOR GREASE INTERCEPTOR GI-1. SEE THE CIVIL DRAWINGS”
- G0.1 says
- “ITEM: GREASE INTERCEPTOR · BY LANDLORD: - · BY TENANT (GC): X · NOTES: LOCATION PER THE LANDLORD'S SITE PLAN”
- Question to send
- Provide the civil drawings and landlord site plan showing the GI-1 location and the exterior grease waste run.
- Why it matters
- P1.0 sends the GI-1 interceptor location and site piping to civil drawings. G0.1 says the grease interceptor location is per the landlord's site plan. Neither sheet is in this set.
- Impact
- High impact
- Sheets
- M1.0 E1.0
- What we found
- MAU-1 to EF-1 hood panel interlock not assigned to any trade
- M1.0 says
- “TAG: MAU-1 · SERVES: KITCHEN HOOD · CFM: 2,900 · HEATING: GAS, 300 MBH INPUT, 55 F DISCHARGE · HP: 2 · DRIVE: DIRECT DRIVE WITH VFD. VFD FURNISHED BY THE MC · VOLTS / PH: 208 / 3 · MCA: 12.0 · MOCP: 15 · WEIGHT: 640 LB · NOTES: INTERLOCK WITH EF-1 AT THE HOOD CONTROL PANEL”
- E1.0 says
- “5. PROVIDE A DISCONNECT WITHIN SIGHT OF RTU-1, MAU-1, EF-1 AND EF-2.”
- Question to send
- Which trade wires and starts up the MAU-1 to EF-1 interlock at the hood control panel?
- Why it matters
- M1.0 requires an interlock between MAU-1 and EF-1 at the hood control panel. E1.0 carries only disconnects within sight of RTU-1, MAU-1, EF-1 and EF-2, with no interlock wiring, control panel or start-up.
- Impact
- High impact
- Sheets
- P1.0 K1.0 E1.0 G0.0
- What we found
- Gas solenoid valve interlocked with hood has no named supplier, installer or wiring
- P1.0 says
- “GAS SOLENOID VALVE, INTERLOCKED WITH THE HOOD SUPPRESSION SYSTEM”
- P1.0 says
- “5. THE GAS SOLENOID VALVE CLOSES WHEN THE HOOD FIRE SUPPRESSION SYSTEM DISCHARGES. MANUAL RESET.”
- K1.0 says
- “ITEM: 7 · QTY: 1 · DESCRIPTION: EXHAUST HOOD, TYPE I, 14'-0", WITH FIRE SUPPRESSION SYSTEM AND HOOD CONTROL PANEL · BY: KES · SET BY: KES · ELECTRICAL: 120V/1, PANEL AND LIGHTS · PLUMBING: - · GAS: - · REMARKS: SUPPRESSION PERMIT BY THE GC. SEE NOTE 4”
- G0.0 says
- “7. KITCHEN EQUIPMENT IS FURNISHED AND SET BY THE KES. FINAL CONNECTIONS BY THE GC'S PLUMBING AND ELECTRICAL CONTRACTORS. SEE K1.0.”
- Question to send
- Who supplies, installs and wires the gas solenoid valve on the gas riser?
- Why it matters
- P1.0 shows a gas solenoid valve that closes on hood discharge. K1.0 gives the hood and suppression to KES with no gas connection, and G0.0 says final connections are by the GC's trades. E1.0 shows no circuit for the valve.
- Impact
- High impact
- Sheets
- G0.1 A1.0 P1.0 S1.0 M1.0
- What we found
- Referenced sheets FA1.0, A5.1, civil and roof plan are not in the set
- G0.1 says
- “11. FIRE ALARM: TENANT NOTIFICATION DEVICES PER FA1.0. THE TIE-IN TO THE BUILDING FIRE ALARM SYSTEM IS MADE BY THE LANDLORD'S FIRE ALARM CONTRACTOR AT THE TENANT'S COST.”
- A1.0 says
- “2 ORDER COUNTER, 36" HIGH, WITH A 36" WIDE ACCESSIBLE SECTION AT 34" AFF. SEE DETAIL 3/A5.1 FOR THE COUNTER SECTION.”
- P1.0 says
- “1-1/2" G UP. ROOF PIPING TO MAU-1 AND RTU-1”
- M1.0 says
- “6. ROUTE ALL GAS PIPING ON THE ROOF ON PIPE SUPPORTS. SEE P1.0 FOR SIZES.”
- S1.0 says
- “ROOF FRAMING PLAN AND NOTES”
- Question to send
- Obtain FA1.0, A5.1, the civil drawings and a roof plan showing drains, vents, flues, intakes, gas piping and roof access before pricing roof and site scope.
- Why it matters
- G0.1 refers to FA1.0 for notification devices and A1.0 refers to A5.1 for the counter section. P1.0 points to the civil drawings for the interceptor, and S1.0 covers framing only with no sheet showing roof drains, vents, flues or roof access.
- Impact
- High impact
- Sheets
- K1.0 S1.0 M1.0 E1.0 G0.0
- What we found
- Walk-in condensing units CU-1 and CU-2 not scheduled, framed, or sized on roof
- K1.0 says
- “8. THE WALK-IN REMOTE CONDENSING UNITS, CU-1 AND CU-2, ARE ROOF-MOUNTED. POWER AND SUPPORTS BY THE GC'S TRADES; SEE MECHANICAL AND ELECTRICAL.”
- K1.0 says
- “WALK-IN COOLER AND FREEZER (ITEMS 15, 16). SEE NOTE 7 REMOTE CONDENSING UNITS CU-1, CU-2 ON THE ROOF. SEE NOTE 8”
- S1.0 says
- “1. THE EXISTING ROOF FRAMING IS ASSUMED TO BE IN GOOD CONDITION AND ADEQUATE FOR THE NEW EQUIPMENT LOADS IN THE EQUIPMENT LOAD TABLE. THE GC SHALL VERIFY THE EXISTING JOIST SIZES, SPACING AND CONDITION BEFORE ORDERING EQUIPMENT, AND REPORT ANY DIFFERENCE TO THE ENGINEER.”
- E1.0 says
- “CKT: 15 · DESCRIPTION: WALK-IN EVAPORATORS (ITEMS 15, 16) · BKR: 20 · BKR: 20”
- G0.0 says
- “4. NEW ROOFTOP EQUIPMENT: RTU-1, MAU-1, EF-1 AND EF-2, WITH NEW ROOF OPENINGS AND FRAMING.”
- Question to send
- Please provide CU-1 and CU-2 weight, curb or stand, roof location, circuit size and refrigerant route, and add them to M1.0, E1.0 and S1.0.
- Why it matters
- K1.0 notes 7 and 8 place walk-in condensing units CU-1 and CU-2 on the roof, with power and supports by the GC's trades. M1.0 schedules only RTU-1, MAU-1, EF-1 and EF-2, the S1.0 load table omits CU-1 and CU-2, and E1.0 shows a circuit only for the evaporators.
- Impact
- High impact
Medium impact 7 items
- Sheets
- E1.0 E2.0
- What we found
- EMT fitting type: set-screw fittings banned on E1.0 but allowed in dry locations on E2.0
- E1.0 says
- “ALL WIRING IN EMT UNLESS NOTED. EMT FITTINGS SHALL BE STEEL COMPRESSION TYPE; SET-SCREW FITTINGS ARE NOT PERMITTED.”
- E2.0 says
- “EMT MAY BE USED WITH STEEL SET-SCREW FITTINGS IN DRY LOCATIONS. USE COMPRESSION FITTINGS IN THE KITCHEN.”
- Question to send
- Which EMT fitting type applies in dry locations, compression or set-screw?
- Why it matters
- E1.0 general note says EMT fittings are steel compression type and set-screw fittings are not permitted. E2.0 note allows steel set-screw fittings in dry locations and requires compression fittings in the kitchen.
- Impact
- Medium impact
- Sheets
- E2.0 E1.0
- What we found
- TC-1 time clock circuit referenced to E1.0 but not shown there
- E2.0 says
- “RESTROOMS, OFFICE, DRY STORAGE AND JANITOR: CEILING OCCUPANCY SENSORS (OS), MANUAL ON, AUTOMATIC OFF AFTER 15 MINUTES. THE EXTERIOR SIGN AND THE STOREFRONT DOWNLIGHTS ARE CONTROLLED BY A 7-DAY ASTRONOMIC TIME CLOCK, TC-1, NEXT TO PANEL LP-1. SEE THE PANEL SCHEDULE ON E1.0 FOR THE TC-1 CIRCUIT. CONNECT EXIT SIGNS AND EMERGENCY LIGHTS AHEAD OF ANY LOCAL SWITCH.”
- E1.0 says
- “CKT: 4 · DESCRIPTION: EXTERIOR SIGN · VA: 600 · BKR: 1 · BKR: 1 · VA: 1,200”
- Question to send
- Ask the engineer to show the TC-1 circuit and the controlled lighting on the panel schedule.
- Why it matters
- E2.0 says the exterior sign and storefront downlights are controlled by TC-1 and sends the reader to the E1.0 panel schedule for the TC-1 circuit. E1.0 has no TC-1 circuit, and circuit 4 is the exterior sign with no time clock control noted.
- Impact
- Medium impact
- Sheets
- A1.0 P1.0
- What we found
- Mop basin MS-1 dimensions differ between plan note and fixture schedule
- A1.0 says
- “4 MOP BASIN MS-1: 36" x 24" FLOOR BASIN WITH A WALL-MOUNTED SERVICE FAUCET AND HOSE BIBB. SEE P1.0.”
- P1.0 says
- “TAG: MS-1 · FIXTURE: MOP SINK · DESCRIPTION: 24" x 24" x 10" FLOOR BASIN, MOLDED STONE, WALL FAUCET WITH VACUUM BREAKER · CW: 1/2" · HW: 1/2" · WASTE: 3" · VENT: 1-1/2"”
- Question to send
- Which MS-1 basin size is correct, 36 in. x 24 in. or 24 in. x 24 in. x 10 in.?
- Why it matters
- A1.0 note 4 gives mop basin MS-1 as 36 in. x 24 in.; the P1.0 fixture schedule gives 24 in. x 24 in. x 10 in. for the same tag.
- Impact
- Medium impact
- Sheets
- K1.0 A4.0 A3.0 M1.0
- What we found
- Stainless cook-line panels: KES to hood bottom on K1.0, GC to ceiling on A4.0
- K1.0 says
- “5. STAINLESS STEEL BACKSPLASH PANELS BEHIND THE COOK LINE, FROM THE TOP OF THE BASE TO THE BOTTOM OF THE HOOD, ARE FURNISHED AND INSTALLED BY THE KES.”
- A4.0 says
- “4. STAINLESS STEEL WALL PANELS AT THE COOK LINE: 18 GA TYPE 304, NO. 4 FINISH, ADHERED TO CEMENT BOARD, WITH STAINLESS TRIM AT ALL EDGES.”
- A3.0 says
- “NO.: 103 · ROOM: KITCHEN · FLOOR: QT-1 · BASE: CB-1 · WALLS: FRP-1; STAINLESS PANELS AT THE COOK LINE, SEE A4.0 · CEILING: ACT-2 · CLG HT: 9'-0" · REMARKS: SEE A2.0, NOTE 2”
- M1.0 says
- “THE HOOD IS 2'-0" HIGH, MOUNTED WITH ITS BOTTOM AT 6'-6" AFF. PROVIDE A STAINLESS STEEL CLOSURE PANEL FROM THE TOP OF THE HOOD TO THE CEILING.”
- A4.0 says
- “STAINLESS STEEL WALL PANELS BEHIND LINE, FROM THE TOP OF THE BASE TO THE BY GC. SEALANT AT ALL JOINTS”
- Question to send
- Who furnishes the stainless cook-line panels, and do they run from base to hood or base to ceiling with a closure above the hood?
- Why it matters
- K1.0 note 5 has KES furnish stainless backsplash from base to hood bottom. A4.0 note 4 and elevation show 18 GA stainless panels by the GC, and M1.0 adds a closure panel from hood top to ceiling.
- Impact
- Medium impact
- Sheets
- K1.0 M1.0 G0.0 S1.0
- What we found
- Grease duct: KES furnishes and MC installs vs MC furnishes and installs
- K1.0 says
- “2. THE HOOD AND THE GREASE DUCT ARE FURNISHED BY THE KES. THE MECHANICAL CONTRACTOR INSTALLS THE GREASE DUCT.”
- M1.0 says
- “GREASE DUCT: 16 GA BLACK STEEL WITH CONTINUOUS LIQUID-TIGHT EXTERNAL WELDS, AND A LISTED 2-HOUR GREASE DUCT ENCLOSURE WRAP FROM THE HOOD TO THE ROOF. THE GREASE DUCT AND THE WRAP ARE FURNISHED AND INSTALLED BY THE”
- G0.0 says
- “5. THE GENERAL CONTRACTOR (GC) IS RESPONSIBLE FOR ALL WORK SHOWN UNLESS IT IS NOTED AS BY THE LANDLORD, BY THE OWNER OR BY THE KITCHEN EQUIPMENT SUPPLIER (KES). SEE THE LANDLORD / / TENANT WORK MATRIX ON G0.1.”
- S1.0 says
- “NEW OPENING FOR THE GREASE DUCT, SEE 2/S1.0”
- Question to send
- Confirm in writing who furnishes and who installs the grease duct and 2-hour wrap.
- Why it matters
- K1.0 note 2 says KES furnishes the hood and grease duct and the MC installs it. M1.0 says the MC furnishes and installs the duct and 2-hour wrap. S1.0 shows a new roof opening for the duct.
- Impact
- Medium impact
- Sheets
- A3.0 A4.0
- What we found
- North accent wall finish level 4 in room 101 schedule vs level 5 in detail
- A3.0 says
- “NO.: 101 · ROOM: DINING · FLOOR: PT-1 · BASE: RB-1 · WALLS: GWB, LEVEL 4 FINISH, PAINT P-1. ACCENT PAINT P-2 AT THE NORTH WALL. · CEILING: ACT-1 · CLG HT: 9'-0" · REMARKS: STOREFRONT EXISTING”
- A4.0 says
- “GWB, LEVEL 5 FINISH, PAINT P-2 (ACCENT), FULL HEIGHT”
- Question to send
- Which finish level, 4 or 5, applies to the north accent wall in room 101?
- Why it matters
- A3.0 room 101 schedule calls for a level 4 gypsum finish with accent paint P-2 at the north wall; the A4.0 north wall detail calls the accent wall a level 5 finish, full height.
- Impact
- Medium impact
- Sheets
- G0.1 A1.0
- What we found
- G0.1 requires 3 accessible seats, but A1.0 shows only 2
- G0.1 says
- “8. ACCESSIBLE DINING SEATING: AT LEAST 5% OF THE 52 SEATS, SO 3 ACCESSIBLE SEATING SPACES ARE REQUIRED, DISPERSED THROUGH THE DINING ROOM.”
- A1.0 says
- “SEATING: ACCESSIBLE SEATING SPACES, AT THE TWO TABLES MARKED "A" · COUNT: 2 · SEATS: 2”
- Question to send
- Confirm the required count and revise the A1.0 layout to 3 spaces, or give the code basis for 2.
- Why it matters
- G0.1 note 8 says 5% of 52 seats requires 3 accessible seating spaces dispersed through the dining room. A1.0 seating summary shows 2 accessible seating spaces at the two tables marked A.
- Impact
- Medium impact
Low impact 2 items
- Sheets
- K1.0 M1.0
- What we found
- Hood suppression permit assigned to GC on K1.0 but hood supplier on M1.0
- K1.0 says
- “ITEM: 7 · QTY: 1 · DESCRIPTION: EXHAUST HOOD, TYPE I, 14'-0", WITH FIRE SUPPRESSION SYSTEM AND HOOD CONTROL PANEL · BY: KES · SET BY: KES · ELECTRICAL: 120V/1, PANEL AND LIGHTS · PLUMBING: - · GAS: - · REMARKS: SUPPRESSION PERMIT BY THE GC. SEE NOTE 4”
- K1.0 says
- “4. THE HOOD FIRE SUPPRESSION SYSTEM IS FURNISHED AND INSTALLED BY THE HOOD SUPPLIER. THE GC OBTAINS THE SUPPRESSION SYSTEM PERMIT.”
- M1.0 says
- “ALL WORK SHALL COMPLY WITH THE 2021 IMC, THE 2021 IFGC AND NFPA 96. THE KITCHEN HOOD AND ITS FIRE SUPPRESSION SYSTEM ARE FURNISHED BY THE KES. THE HOOD FIRE SUPPRESSION SYSTEM PERMIT IS OBTAINED BY THE HOOD SUPPLIER.”
- Question to send
- Who obtains and pays for the hood fire suppression permit: the GC or the hood supplier?
- Why it matters
- K1.0 item 7 and note 4 say the GC obtains the suppression permit. M1.0 says the hood fire suppression permit is obtained by the hood supplier.
- Impact
- Low impact
- Sheets
- A1.0 A5.0
- What we found
- Floor transition max 1/4 in. against 1/2 in. threshold at door 101
- A1.0 says
- “5. ALL FLOOR TRANSITIONS SHALL BE FLUSH OR BEVELED PER ICC A117.1. MAXIMUM 1/4" VERTICAL CHANGE.”
- A5.0 says
- “1 THRESHOLD, 1/2" MAX. HEIGHT, BEVELED”
- Question to send
- Which maximum height applies at the door 101 threshold, 1/4 in. or 1/2 in.?
- Why it matters
- A1.0 note 5 allows a maximum 1/4 in. vertical floor change; A5.0 threshold note for door 101 allows a 1/2 in. maximum height.
- Impact
- Low impact